US2009188172A1PendingUtilityA1
Ballasted storm water retention system
Est. expiryJan 24, 2028(~1.5 yrs left)· nominal 20-yr term from priority
E04D 11/00E04D 13/0477
45
PatentIndex Score
0
Cited by
0
References
0
Claims
Abstract
A roof system designed to retain water during storms and release it slowly over a period of time includes a polymeric water impervious membrane covered with a drainage board in turn covered with a water retention mat. The water retention mat and drainage board are held in position by ballast, preferably gravel. The mat is designed to retain at least about 25% of a one-inch per hour rainfall and release it gradually over 2 to 3 hours, thereby reducing rain runoff during storms and reducing the load on a storm sewer system
Claims
exact text as granted — not AI-modified1 . A roof system comprising in the following order:
a roof deck; a waterproof layer covering said roof deck; a drainage member providing flow channels covering said waterproof layer; a moisture retention mat supported by said drainage member; and ballast covering said moisture retention mat.
2 . The roof system claimed in claim 1 wherein said drainage member comprises rigid spacers fixed to a water permeable layer.
3 . The roof system claimed in claim 2 wherein said moisture retention mat comprises a nonwoven polymeric mat.
4 . The roof system claimed in claim 3 wherein said nonwoven polymeric mat retains at least about 0.2 gallons of water per square foot.
5 . The roof system claimed in claim 2 wherein said ballast comprises gravel.
6 . The roof system claimed in claim 1 comprising an insulation layer between said roof deck and said waterproof layer.
7 . The roof system claimed in claim 1 further comprising a protective mat between said drainage member and said waterproof layer.
8 . The roof system claimed in claim 3 wherein said waterproof layer comprises a polymeric membrane.
9 . A roof system wherein the outermost three layers consist of ballast covering a water retention matting covering a water drainage member.
10 . A roof system comprising in the following order:
a roof deck; a waterproof layer covering said roof deck; a drainage member providing water flow paths; a moisture retention mat supported by said drainage member; and ballast covering said mat.Cited by (0)
No later patents cite this yet.
References (0)
No backward citations on record.