Abstract
A floating LNG plant including a first and a second converted LNG carrier each provided with a hull and at least one LNG storage tank wherein the floating LNG plant further includes: a connection structure for connecting the hull of the first and the second converted LNG carrier in order to obtain a twin-hull vessel; process equipment for LNG processing on the floating LNG plant; and a mooring system for mooring the floating LNG plant to the seabed, wherein the at least first and second converted LNG carrier each include an LNG carrier, originally provided with a plurality of LNG tanks, wherein at least one LNG tank has been deactivated and/or removed from at least one LNG carrier to create space on the floating LNG plant for installing the process equipment for LNG processing.
Claims
exact text as granted — not AI-modified1 . A floating liquefied natural gas (LNG) plant, comprising:
a first and a second converted LNG carrier each provided with a hull and at least one LNG storage tank, the at least first and second converted LNG carrier each comprising an LNG carrier, originally provided with a plurality of LNG tanks, at least one LNG tank having been deactivated and/or removed from at least one LNG carrier to create space on the floating LNG plant for installing the process equipment for LNG processing; a connection structure configured to connect the hull of the first and the second converted LNG carrier in order to obtain a twin-hull vessel, the connection structure providing additional deck space between the hull of the first and the second converted LNG carrier; process equipment for LNG processing on the floating LNG plant, the process equipment being at least partially installed on the additional deck space provided by the connection structure; and a mooring system for mooring the floating LNG plant to the seabed.
2 . The floating LNG plant according to claim 1 , wherein the mooring system is provided with a turret configured to allow the floating LNG plant to weathervane.
3 . The floating LNG plant according to claim 2 , wherein the turret is placed external of each of the hulls of the first and second LNG carrier.
4 . The floating LNG plant according to claim 1 , wherein the floating LNG plant is connected via a flexible riser to the seabed for the transfer of gas between the plant and the seabed.
5 . The floating LNG plant according to claim 1 , wherein the first and the second converted LNG carrier are connected to be essentially parallel.
6 . The floating LNG plant according to claim 1 , wherein the process equipment for LNG processing comprises means for liquefaction of natural gas.
7 . The floating LNG plant according to claim 1 , further comprising a reservoir configured to store fluids separated during the LNG processing, the reservoir being positioned in the connection structure between the first and the second converted LNG carrier.
8 . The floating LNG plant according to claim 1 , further comprising at least one sponson to create additional hull volume.
9 . The floating LNG plant according to claim 1 , further comprising transfer devices configured to load or unload hydrocarbon liquids produced as a by-product of the LNG process.
10 . The floating LNG plant according to claim 1 , further comprising LNG transfer devices configured to load or unload LNG.
11 . A method for converting a first and a second liquefied natural gas (LNG) carrier into a floating LNG plant, the LNG carrier including at least a hull and a plurality of LNG storage tanks, the method comprising:
removing from the first and/or second LNG carrier at least one LNG tank, to obtain a first and a second converted LNG carrier; connecting the first and the second converted LNG carrier by a connection structure in order to obtain a twin-hull vessel; connecting the connection structure between the hull of the first and the second converted LNG carrier in order to create additional deck space; installing process equipment for LNG processing on the twin-hull vessel, the process equipment being at least partially installed on the additional deck space provided by the connection structure; and installing a mooring system on the twin-hull vessel for mooring the floating LNG plant to the seabed.
12 . The method according to claim 11 , further comprising providing the mooring system with a turret to allow the floating LNG plant to weathervane.
13 . The method according to claim 11 , further comprising connecting the first and the second converted LNG carrier to be essentially parallel.
14 . The method according to claim 11 , wherein the process equipment for LNG processing comprises means for liquefaction of natural gas.
15 . The method according to claim 11 , further comprising providing a reservoir for storing fluids separated during the LNG processing, said reservoir being positioned in the connection structure between the first and the second converted LNG carrier.
16 . The method according to claim 11 , further comprising providing the floating LNG plant with at least one sponson to create additional hull volume.
17 . The method according to claim 11 , further comprising providing the floating LNG plant with LNG transfer devices for loading or unloading LNG.
18 . The method according to claim 11 , further comprising producing the floating LNG plant with transfer devices for loading or unloading hydrocarbon liquids, which are produced as a by-product of the LNG process.Join the waitlist — get patent alerts
Track US2016214687A1 — get alerts on status changes and closely related new filings.
We store only your email — no account needed. See our privacy policy.