A process for safely excavating to reveal underground utilities. The process includes the steps of: identifying known utilities; planning an excavation trench; excavating the trench by: (i) making a cut of the excavation trench at a selected depth; (ii) extracting material from the trench; (iii) observing the trench; (iv) adjusting the depth of cut; and repeating (i) to (iv) until the process is complete.
Claims
exact text as granted — not AI-modified1 . A process for exposing underground utilities in an excavation zone which may contain known utilities and unknown utilities including the steps of:
identifying known utilities; planning an excavation trench taking into account known utilities; excavating the trench by:
(i) making a cut of the excavation trench at a selected depth;
(ii) extracting material from the trench;
(iii) observing the trench to identify signs of the presence of a utility;
(iv) adjusting the depth of cut based on the outcome of the observation such that the depth of cut is reduced at the first signs of the pressure of a utility and further reduced as the cut approaches the utility; and
repeating (i) to (iv) until the process is complete.
2 . The process of claim 1 wherein the step of identifying known utilities includes one or more of: checking records of utility locations; tracing likely utility routes from known nodes; tracing utilities using ground penetrating radar or other subterranean mapping techniques.
3 . The process of claim 1 wherein the step of planning the trench includes selecting a trench location to minimise disruption of known utilities.
4 . The process of claim 1 wherein the step of planning the trench includes marking the selected trench location on the ground together with known utility locations and depth.
5 . The process of claim 4 wherein the marking of known utility locations and depths are colour coded to maximise visibility.
6 . The process of claim 1 wherein the step of a making a cut of the excavation trench is performed by a mechanical saw that has controllable depth of cut.
7 . The process of claim 6 wherein the first cut of a new trench is at a depth of 50 mm or 45 mm or 40 mm or 35 mm or 30 mm or 25 mm or 20 mm or 15 mm or 10 mm or 5 mm.
8 . The process of claim 6 wherein a location of the mechanical saw is controllable in the X direction (advancement along the trench), Y direction (lateral position of the cut) and Z direction (depth of cut).
9 . The process of claim 1 wherein the step of extracting material from the trench uses a vacuum excavation machine.
10 . The process of claim 9 wherein the step of extracting material from the trench uses a vacuum excavation machine and the vacuum excavation machine follows closely behind the mechanical saw to continuously remove material from the trench.
11 . The process of claim 9 wherein the vacuum excavation machine is a hydro excavator that can operate in a low pressure mode of about 200 psi and a high pressure mode of about 2000 psi.
12 . The process of claim 1 wherein the step of observing the trench includes observing the bottom and/or sides of the trench to identify any sign of the presence of a utility.
13 . The process of claim 12 wherein the signs include one or more of: change in colour; change in material; cracking, pitting or lifting.
14 . The process of claim 1 wherein the step of adjusting the depth of cut is based on the observation of the trench.
15 . The process of claim 14 wherein the adjustment to the depth of cut is 0 mm.Join the waitlist — get patent alerts