Method of excavating a tailings lagoon
Abstract
A method of dewatering a tailings lagoon retained by a dam comprising: excavating an excavation hole in the tailings lagoon; allowing water from surrounding tailings to enter the excavation hole; and pumping water in the excavation hole out of the excavation hole and discharging beyond a toe of the dam. Also disclosed is a method comprising: excavating a channel in a tailings lagoon from a shore of the tailings lagoon and floating a pontoon in water in the channel from the shore along the channel,wherein: excavating involves breaking down solid tailings in the tailings lagoon into a slurry using water and removing the slurry using a submersible slurry pump mounted on the pontoon.
Claims
exact text as granted — not AI-modified1 . A method comprising:
excavating a channel in a tailings lagoon from a shore of the tailings lagoon and floating a pontoon in water in the channel from the shore along the channel, wherein: excavating involves breaking down solid tailings in the tailings lagoon into a slurry using water and removing the slurry using a submersible slurry pump mounted on the pontoon.
2 . The method of claim 1 , wherein:
during the excavating the water for breaking down the solid tailings is supplied by the pontoon.
3 . The method of claim 2 , wherein:
the water supplied by the pontoon is at least partly water extracted from the channel by the pontoon.
4 . The method of claim 1 wherein:
during the excavating water is provided to the pontoon from a shore of the tailings lagoon.
5 . The method of claim 1 , wherein:
water is supplied to the channel during excavation from beyond the tailings lagoon.
6 . The method of claim 1 , wherein:
the amount of water contained in the slurry (density) is controlled to be a certain level.
7 . The method of claim 6 , wherein:
the amount of water contained in the slurry is controlled by varying the depth below the pontoon of the slurry pump.
8 . The method of claim 6 , wherein:
the amount of water contained in the slurry is controlled by varying the flow rate of water used in breaking down solid tailings.
9 . The method of claim 6 wherein:
the amount of water contained in the slurry is controlled by varying a flow rate of water provided to the slurry pump and discharged by the slurry pump.
10 . The method of claim 6 , wherein:
the removed slurry travels from the slurry pump to a discharge point along a pipe and the amount of water contained in the slurry in the pipe is controlled by varying the amount of water added to the pipe at a position between the slurry pump and the discharge point.
11 . The method of claim 1 , wherein:
the pontoon is controlled remotely from a shore of the tailings lagoon.
12 . The method of claim 1 , wherein:
a water jet propels the pontoon along the channel.
13 . The method of claim 1 , wherein a plurality of water jets on the pontoon control the pontoon directionally.
14 . The method of claim 1 , wherein the removed slurry is reprocessed to remove a material contained in the slurry.
15 . A method of dewatering a tailings lagoon retained by a dam comprising:
excavating an excavation hole in the tailings lagoon; allowing water from surrounding tailings to enter the excavation hole; and pumping water in the excavation hole out of the excavation hole and discharging beyond a toe of the dam.
16 . The method of claim 15 , wherein:
a pontoon floats in water in the excavation hole and supports equipment used for the step of pumping water.
17 . The method of claim 15 , wherein:
before excavating the excavation hole, the pontoon is floated along a channel in the tailings lagoon to the location at which the excavation hole is to be excavated using the method of claim 1 .
18 . The method of claim 15 , wherein:
dewatering is localised to tailings adjacent the dam.Join the waitlist — get patent alerts